Handover and defect repairs: confirm the start date first
Jayden Tay · REN 64148
2026-11-07 · 2026-11-16
When the developer’s vacant-possession notice arrives, most clients first ask, “When can I get the keys?” I’d add: check the date on the notice first. Both the defect liability period and late-delivery compensation hinge on which day counts as the day you took vacant possession.
This article covers new homes in Peninsular Malaysia that are regulated by housing development law and use the standard Schedule G or H contract. It doesn’t apply as-is to Sabah, Sarawak or other contracts.
Getting the keys doesn’t mean every condition has been met
Under the statutory standard contract, vacant possession goes hand in hand with the Certificate of Completion and Compliance (CCC), water and electricity being ready for connection, and other conditions. Receiving the keys doesn’t mean all of those have been met.
Once you get the notice, keep these safe: the vacant-possession notice (note the date), your sale and purchase agreement (SPA), and the defect-reporting channel the developer has given you.
Even if you don’t collect the keys, the clock may already be running
Many people assume that if they don’t collect the keys, the clock doesn’t start. In fact the contract says that once 30 days have passed after the developer’s notice, you may be treated as having taken vacant possession even if you haven’t collected the keys or moved in.
So when the notice comes, don’t just leave it.
The defect liability period is usually 24 months
Under the standard contract (Schedules G and H), the defect liability period is generally 24 calendar months from vacant possession.
During this period, if a problem appears because of poor workmanship, faulty materials or a departure from the approved plans, the developer must fix it at its own cost within 30 days of your written notice.
If it isn’t fixed within 30 days, the contract sets out a next step: you can notify the developer that you intend to carry out the repair yourself and roughly what it will cost, then give the developer another 30 days to act.
Twenty-four months doesn’t mean “two years from move-in, covering everything”. It depends on whether the problem falls into the categories above. Don’t withhold money that’s due just because there’s a defect. Whether a notice is valid and whether the conditions are met is best checked by a lawyer against the documents.
First inspection: safety first
On your first inspection, stick to what you can see and touch: do doors and windows open and close properly, are there cracks in the walls, is there visible seepage in the kitchen and bathrooms, and are socket covers and railings obviously damaged?
Don’t open the DB box, touch wiring, or shake railings hard, and don’t turn on the water to test things without asking first. If you see exposed wiring, a clearly unstable railing or a serious leak, stop, inform the developer or management office, and get a qualified person to deal with it.
Reporting defects: one item per line, clearly written
For each item, note the location, the problem, the photo number, the date you found it and the date you reported it. Send the written notice to the party, and in the way, the contract specifies.
You can use WhatsApp to communicate, but don’t assume it replaces the notice the contract requires. If you’re asked to sign an “all repairs done” form or anything that waives your rights and you don’t understand it, have a lawyer explain it before you sign.
Before you renovate
If a leak hasn’t been properly investigated, don’t rush to close up the ceiling or lay flooring. In an apartment, you need the management’s written approval before renovating, and where required, approval from the relevant authority too. For how to prepare for renovation, see Renovating a new home: check the contractor, ask about approvals, then split the budget.
For how late-handover compensation is calculated and the deadlines for going to the tribunal, see New home handed over late? How to work out your LAD compensation. Once the defect liability period ends, that doesn’t necessarily mean nothing more can be done; whether a particular case can still be pursued is a question for a lawyer.
Should you hire someone to inspect the unit?
| Your situation | My view |
|---|---|
| You’re in Singapore or elsewhere and don’t have time to check every item | Consider hiring an inspector, but read the report yourself, then send the developer written notice as the contract requires |
| You’re careful, have time, and the unit isn’t big | Inspecting it yourself with a checklist is fine |
| It’s a landed house, or you’ve already seen seepage or cracks | Getting a qualified person to look is better than guessing |
An inspection report doesn’t replace the written notice the contract requires, and time still runs from the date you took vacant possession. This site does not recommend any inspection company.
Once the vacant-possession notice arrives, follow this order
- Check the date on the notice and work out the date 30 days later.
- Book a time to take vacant possession, bring a checklist and a camera, and note down the water and electricity meter readings.
- List the defects one per line, send them as the contract specifies, and keep a copy.
- Go back 30 days later to see whether they’ve been fixed. If not, ask a lawyer about next steps.
- Put the end date of the 24-month defect liability period in your calendar, do a full inspection again before it ends, and report the final batch of issues.
The above is general information, not legal advice. Your contract and your lawyer’s advice are what count.
Source
- National Housing Department enforcement frequently asked questions (Schedules G and H defect-liability period of 24 calendar months; 30-day repair)
- Housing Development (Amendment) Regulations 2015 (vacant-possession conditions; deemed vacant possession 30 days after notice; self-repair procedure)
- Strata Management (Maintenance and Management) Regulations 2015 (Third Schedule: written approval of the management must be obtained before renovation)
Related reading
- What to inspect on the day you collect the keys: a handover checklist
- Getting a water meter for a new home in Johor: new connection or just a change of account name?
- After the developer hands over the keys, when is the JMB formed, and what should buyers watch?