New home handed over late? How to work out your LAD compensation
Jayden Tay · REN 64148
2026-11-09 · 2026-11-16
If you have bought a new home, the news you least want to hear is: “Handover is going to be late.”
Projects run late for all sorts of reasons, so don’t go in angry. The practical move is to check your contract first, work out how much late-delivery compensation you are owed, and then sit down and talk it through with the developer. This compensation is usually called LAD (liquidated ascertained damages).
This article covers new residential homes in Peninsular Malaysia (and Labuan). It does not apply as-is to Sabah, Sarawak or commercial property.
Start with the handover date in your contract
For new homes in the Peninsula, the sale and purchase agreement (SPA) usually follows the government’s standard form. Landed homes use Schedule G, with handover within 24 months of the agreement date. Strata homes such as apartments use Schedule H, with handover within 36 months of the agreement date.
That is the standard wording, but you still need to open your own contract and check. If someone tells you “the handover date has been changed”, ask for it in writing and have a lawyer look at whether the change is valid.
How LAD is calculated
The Tribunal for Homebuyer Claims (TTPR) gives a simple formula: days late × purchase price × 10% ÷ 365.
Here is the official example. The count starts the day after the contractual deadline and runs until the day you take vacant possession under the contract.
| Item | Official example |
|---|---|
| Purchase price | RM300,000 |
| Days late | 100 days |
| Calculation | 100 × RM300,000 × 10% ÷ 365 |
| Compensation (approx.) | RM8,219.18 |
Getting the keys is not necessarily the day you take vacant possession. The contract also has conditions such as the certificate of completion and compliance (CCC) and water and electricity being ready for connection, and there is a rule that vacant possession is treated as taken once a set period has passed after the notice. Which day the count stops has to be checked against the contract and the notice.
Under the contract, the developer pays this compensation, and it can also be set off against the instalments you have yet to pay. Before you deduct anything, check with the lawyer handling your purchase. Keep paying your bank housing loan every month as normal — don’t stop on your own.
How to raise it with the developer
The usual first step is to write to the developer.
Send an email or letter setting out the agreement date, the handover deadline, the date you actually took possession, the number of days late, and the amount you have worked out. Attach copies of the SPA and the vacant-possession notice, and keep proof that you sent it.
If you can’t agree
If the amount is RM50,000 or less, you can file a claim with the Tribunal for Homebuyer Claims (TTPR). The filing fee is RM10. Use the forms and filing method shown on the official website at the time.
If it is more than RM50,000, you can consider going to court; speak to a lawyer first. TTPR can also hear a larger claim if both sides agree to it in writing.
RM50,000 is the limit for a single TTPR claim. It does not mean late-delivery compensation is capped at that amount.
TTPR deals with residential homes (including terrace houses, apartments, condos, SOHO and so on). It does not handle commercial property, abandoned projects, agent fraud or landlord–tenant disputes.
Don’t miss the filing deadline
You generally have 12 months to file with TTPR, counted from:
| Type of claim | Counted from |
|---|---|
| LAD and other contractual claims | The day the CCC is issued |
| Technical defects in the home | The day the defect liability period ends |
| Contract terminated before the CCC was issued | The day the contract was terminated |
Once your case is clear, take the CCC, the SPA and the vacant-possession notice to TTPR early. Don’t leave it to the last minute.
Questions worth asking
- “What handover date does my contract give? Is there a valid extension in writing?”
- “When was the CCC issued? Does it cover my block?”
- “From which day to which day is LAD counted? Can you set out the days and the amount in writing?”
- “Will the compensation be paid to me directly or deducted from the purchase price? How will the lawyer handle it?”
For what else to check at handover, see Handover and defect repairs: confirm the start date first. Late-delivery compensation and defect repairs are separate issues, so deal with them separately. To check a developer before you sign, see Before buying a new home, how do you check the developer licence and advertising permit? For how much cash you need around handover, see How much money do you really need to buy a new home?
The above is general information, not legal advice. Your contract and your lawyer’s advice are what count.
Source
- Tribunal for Homebuyer Claims (TTPR) frequently asked questions (LAD formula and example; RM50,000 per claim and the written-consent exception; three types of application time limit; jurisdiction and exclusions; forms and RM10)
- National Housing Department enforcement frequently asked questions (TTPR / civil routes when the developer does not pay LAD; the relationship between the calculation and taking vacant possession)
- Statutory schedules to the 2015 Housing Development (amendment) Regulations (Schedule G: 24 months; Schedule H: 36 months; 10% a year calculated daily; the date of taking possession and the deduction arrangement)
- Text of Act 118 (provided by KPKT) (section 16N: the tribunal’s jurisdiction and time limits)
Related reading
- What to inspect on the day you collect the keys: a handover checklist
- How the Homebuyer Tribunal differs from the Strata Management Tribunal, and which disputes can go there
- Is freehold always better? When buying in Johor Bahru, look past the label
Was this article helpful?