If the project is already abandoned, what should a buyer do next?
Jayden Tay · REN 64148
2026-11-13
The hoarding has been shut for months, the machinery is gone, but the bank is still charging interest during construction. What sales once said — “the government will definitely take over” — no longer lines up. Many buyers’ first reaction is to stop the loan payments themselves, or to rush a claim to the Tribunal for Homebuyer Claims. Both of those steps can be the wrong ones.
Whether a project is officially abandoned depends on confirmation by the Ministry of Housing and Local Government, and on the abandoned-project list on TEDUH on the day you check. Until that is confirmed, do not stop your home loan payments on your own. The Tribunal for Homebuyer Claims also states in plain terms that abandoned projects are outside its jurisdiction.
This article is about what to do after you have already bought, and the works have stopped. For the signals to check before you buy, see How to check for an abandoned project: the signals to look at before you buy. For how late vacant-possession compensation is calculated, see New home handed over late? How to work out LAD compensation. This article applies to new residential homes in Peninsular Malaysia and Labuan that are governed by the Housing Development (Control and Licensing) Act 1966 (Act 118). Do not apply it directly to Sabah, Sarawak or commercial buildings.
How do you confirm it has officially been listed as abandoned?
A worksite that looks as if it has stopped is not the same thing as a project that has officially been listed as abandoned. The National Housing Department defines a “sick project” and an “abandoned project” separately.
A sick project (projek sakit) is one where progress lags the progress that should have been achieved by more than 30%, or where the period in the sale and purchase agreement (SPA) has already expired. It needs to be monitored, but it is not yet abandoned.
An abandoned project (projek terbengkalai) has to meet the conditions written by the Housing Department, and be certified by the Minister. The Department’s definition is: the project is still not completed, within or outside the SPA period, and there has been no significant activity at the worksite for six continuous months; or a winding-up petition has been registered in the High Court (the Housing Department page cites section 218 of the Companies Act 1966); or the company has been placed under a Receiver and Manager; or the developer has admitted in writing to the Controller of Housing that it is unable to continue. On top of those situations, the Minister must still certify, under section 11(1)(ca) of Act 118, that the housing development has been abandoned.
There is one point that is easy to misread. Some older Housing Department pages still write section 11(1)(c). In the text of the Act, the power to certify that the licensed housing developer has abandoned the housing development is section 11(1)(ca). Section 11(1)(c) is a different power: with the concurrence of the Minister of Finance, to direct a company to assume control of and carry on the business of the housing developer.
For the lists and the status, follow the latest information on TEDUH on the day you check. Abandoned projects are published by category, for example “in planning”, “being rehabilitated” and “static”. The lists are updated. This article does not transcribe any full list, and does not single out a particular project as an example. When you check, match the developer company’s full name and the project’s full name together. The National Housing Department’s reports page states that the status of abandoned projects and sick projects is looked up on TEDUH; that page shows an update on 2026-02-09, and when it was checked on 2026-11-13 it still pointed to TEDUH.
What is more immediate for a buyer is to apply to the Abandoned Project Rehabilitation Division for a Confirmation Letter of an Abandoned Project (Surat Pengesahan Projek Terbengkalai). The Housing Department FAQ states that this letter can help you apply to your lending bank for it to consider a lower interest rate or a restructuring of repayments, apply to the Employees Provident Fund for a second housing withdrawal, and deal with the loan under the rules then in force at the Public Sector Home Financing Board (LPPSA). Before you apply, first confirm that the project is already on the official abandoned list, and attach copies of your identity card and the SPA. Use the contact details on the Housing Department page on the day you apply.
If the project has not yet been formally listed as abandoned, the Housing Department states: buyers generally cannot apply for a second EPF housing withdrawal; public servants generally also cannot apply to freeze repayments under the Treasury circular; and an application to the end-financing bank to restructure or defer repayment generally also does not have the basis that this confirmation letter is meant to support. So confirming the official status comes before arguing with the bank.
After you have the documents together, do it in this order
Do not throw away receipts, progress billings, drawdown notices or site photographs. Put the SPA, payment receipts, progress claims, architect’s or engineer’s certificates, the loan agreement and each drawdown notice, written correspondence with the developer, and dated site photographs, in time order. Later, whether you are complaining, filing a proof of debt with the liquidator, or talking to the bank about a restructuring, you will need these documents.
Second, go to TEDUH with the company’s full name and the project’s full name, match them against the lists, and check the developer licence and the advertising permit. For how to check the licence, see Before buying a new home, how do you check the developer licence and advertising permit?
Third, complain to the Ministry of Housing and ask about the rehabilitation progress. In the TEDUH FAQ, the National Housing Department points comments, complaints and enquiries about the Department to the Public Complaints Management System (SISPAA). The Housing Department’s FAQ on abandoned housing also lists the email and other contact details of the Abandoned Project Rehabilitation Division. Item 11 of the enforcement FAQ states that the current rehabilitation progress of an abandoned project is to be queried with that Division. Use the complaint channels and forms published on the official site on the day you file. Do not let an oral promise in a chat app stand in place of a written record.
Fourth, be clear which windows cannot deal with this. The official FAQ of the Tribunal for Homebuyer Claims (TTPR) states that abandoned projects are outside its jurisdiction. TTPR only hears residential claims in Peninsular Malaysia and Labuan that arise from a sale and purchase agreement between a purchaser and a housing developer. The limit is RM50,000 per claim; a claim above that amount can only be heard if both parties have agreed in writing. Filing fees, forms and how to submit them follow what the official site publishes on the day. If the home is later actually handed over, how late-delivery compensation is calculated, and whether there is a 12-month time limit, go back to the late vacant-possession article. Do not treat that method of calculation as the way into an “abandoned project case”.
Fifth, ask a lawyer to look at the contract and the limitation period, then decide whether to go to court, and whether the statutory right to terminate applies. Item 4 of the Housing Department enforcement FAQ states that buyers may take court action against the developer based on the terms of the SPA. Section 8A of Act 118 adds a statutory right to terminate: if, after the SPA is executed, the licensed housing developer refuses to carry out, or delays, suspends or ceases, work for a continuous period of six months or more, the purchaser may terminate the agreement provided the written consent of the end financier has been obtained and the Controller of Housing has certified that stoppage. The developer must, within 30 days of the termination, refund to the purchaser all monies received, free of any interest. The financier shall not unreasonably withhold its written consent. This section applies only to an agreement lawfully entered into after the relevant amending Act came into operation. For the commencement date, follow the text on the Federal Legislation portal on the day you check. Whether your agreement falls into this class, and how the Controller’s certificate is applied for, ask a lawyer first. Do not treat a letter you have written yourself as if the agreement has already been terminated.
If the developer has already gone into winding-up, the Housing Department advises buyers, before the limitation period expires, to make a claim against the developer by registered post, or to file a Proof of Debt with the Malaysian Department of Insolvency. That FAQ item cites the Limitation Act 1953, and describes the period as six years from the date the SPA was signed. The exact cut-off date can differ with the time of the breach and the facts of the case. Do not work out a deadline yourself from that wording. Ask a lawyer to look at your documents.
Buyers in the same phase are better off acting together. You can form or join a purchasers’ committee, and deal with the Ministry, the rehabilitation developer or the liquidator as a group, so that people are not each given a different oral version. The National House Buyers Association (HBA) can offer information or help with coordination, but it is a voluntary, non-profit, non-governmental organisation, not a government department. A letter from HBA cannot take the place of the Ministry’s confirmation letter, and cannot take the place of a decision by the Tribunal or the court.
Do you still have to keep paying the loan? Can you claim?
One sentence first: until you have written agreement from the bank, do not stop the loan payments on your own.
When you buy a home that is still being built, the bank usually releases the approved portions to the developer in line with progress, and may charge interest during construction only on the amounts already released. Not having the keys yet does not mean nothing will be deducted this month. For how interest during construction is calculated and who pays it, see A new home still being built: who pays the interest during construction, and what do you repay each month?, and follow the contract and the drawdown notices between you and Maybank, CIMB, Public Bank, RHB or your other Malaysian lending bank.
The Housing Department states that the abandoned-project confirmation letter can help a buyer apply to the financier for it to consider a lower interest rate and a restructuring of repayments. That is an application for the other side to consider it. It is not an automatic stop on the loan, and it is not an automatic cancellation of the contract. When this was checked on 2026-11-13, no general Bank Negara rule was found that requires a bank, just because a project is abandoned, to stop deductions or to write off the loan. What you should do is send the confirmation letter, the SPA and the drawdown records in writing to your own lending bank, and keep the bank’s written reply.
For the Public Sector Home Financing Board (LPPSA), the Housing Department is more specific: once you have the confirmation letter, you may, under the rules then in force, apply to cancel the existing loan and apply for a new loan, or apply to defer the charging of loan interest during the rehabilitation period or for five years, whichever is earlier. The interest rate written on that Housing Department page is 4%. Figures and conditions of this kind change. Whether the rate is still 4%, and how to apply, follow the LPPSA official site on the day, and put the application in writing. The arrangement in Treasury Circular No. 12 of 2005, about public servants freezing repayments, is likewise discussed only on the footing that the project has already been formally declared abandoned. For the current practice, follow the Treasury or LPPSA text on the day you check.
For a second Employees Provident Fund housing withdrawal, the confirmation letter only helps you make the application. Whether it is approved still depends on the EPF’s rules on the day, so follow the official KWSP site.
Some people ask whether they can claim on Mortgage Reducing Term Assurance (MRTA) or Mortgage Level Term Assurance (MLTA) and settle the loan. Policies of this kind usually pay the bank, on the death or total permanent disability of the borrower, to reduce or settle the outstanding loan then due. The works stopping, or the project being listed as abandoned, is not in itself generally a reason for a claim under this kind of policy. Do not treat “the project is abandoned” as a reason to claim on MRTA. For the difference between MRTA and MLTA, see What is the difference between MRTA and MLTA, and how do you choose? If the owner has already died, the loan, the policy and the estate have to be looked at separately; see After the owner dies, does the home loan still have to be repaid?
How does rehabilitation work, and do buyers usually have to pay more?
The Ministry has an Abandoned Project Rehabilitation Division, which issues confirmation letters and coordinates rehabilitation. The Division assesses, from the technical and financial angles, whether a project can be revived, and whether the rehabilitation costs put forward by a rescue developer or contractor add up, then submits the proposal to the technical and financial committee. Some projects bring in a rescue developer or contractor, some involve a government development allocation, and some have to be dealt with together with the liquidator, including the Housing Development Account, the transfer of title and vacant possession. The finance unit also coordinates meetings with the lending bank, the developer, the liquidator and the buyers. If the list says “being rehabilitated”, that only means the project has been placed in that category. It does not guarantee a new vacant-possession date. Ask clearly who is doing the work, how far it has got, and whether there is a written timetable.
There is no single official figure for whether buyers have to pay more. The tax appendix to Budget 2027 treats “additional financing by the original purchaser” as one kind of document related to rehabilitation. For the rehabilitation of abandoned projects confirmed by the Ministry of Housing, it proposes a 100% stamp duty exemption on loan agreements and instruments of transfer completed by the rescue contractor or developer, and by the original purchaser, between 1 January 2027 and 31 December 2030. A similar exemption previously applied to documents completed from 1 January 2013 to 31 December 2025. That only shows that the official side recognises that some rehabilitation schemes may require the original purchaser to take further financing. It does not mean every project requires a fixed extra sum.
Any additional payment should be in that project’s written official rehabilitation scheme, and should come with an explanation from your own lawyer. Do not transfer money to a personal account just because someone is collecting funds in a buyers’ group, or because someone says orally that “if you do not pay, you are out”. Whether stamp duty is exempt, and whether the exemption window covers the date of your documents, follow what the Ministry of Finance or the Inland Revenue Board publishes on the day.
If the developer is already in winding-up, the liquidator will come into the rehabilitation and the arrangement of claims. Buyers should still, as the Housing Department advises, ask a lawyer first about limitation, and file a proof of debt with the Department of Insolvency when that is needed. Do not assume that once the company is wound up, the government will automatically finish the building, or that the loan will automatically disappear.
Common misconceptions
“The site has stopped, so it is officially abandoned.” It still has to meet the Housing Department’s definition, be certified by the Minister, and appear on the official list on the day you check, or in a confirmation letter.
“The government has announced rehabilitation, so you will definitely get the home on time.” The rehabilitation list only states the category. It does not guarantee a new vacant-possession date.
“You can take an abandoned project to the Tribunal for Homebuyer Claims.” The Tribunal’s official FAQ lists abandoned projects as being outside its jurisdiction.
“If I stop the payments first, the bank will cancel the loan.” The confirmation letter only helps you apply for the other side to consider a restructuring or an adjustment of interest. No general Bank Negara rule requiring an automatic stop on the loan was found. Without the bank’s written agreement, do not stop the payments yourself.
“If the project is abandoned, I can claim on MRTA.” MRTA or MLTA is usually protection on death or total permanent disability, not compensation for the works stopping.
“The National House Buyers Association is a government department, and its letter is as good as official confirmation.” HBA is a non-governmental organisation. The official confirmation letter is issued by the Ministry’s Abandoned Project Rehabilitation Division.
“During rehabilitation the government will pay all the costs, and buyers will certainly not have to pay more.” The Budget itself mentions that original purchasers may need additional financing. Whether you have to pay, and how much, follows that project’s written rehabilitation scheme.
What to do next
- Gather the SPA, receipts, progress billings, drawdown notices, written correspondence and dated site photographs, and give a copy of the set to a lawyer.
- Using the company’s full name and the project’s full name, match them against the abandoned-project and sick-project lists on TEDUH on the day you check, and check the licence.
- If the project is already on the list, apply for the abandoned-project confirmation letter. At the same time, complain to the Ministry through the channels published on the official site that day, and ask the Rehabilitation Division about progress.
- With the confirmation letter, apply in writing to your own lending bank — for example Maybank, CIMB, Public Bank or RHB — for it to consider a restructuring or an adjustment of interest, wait for a written reply, and do not stop the payments yourself. Public servants should apply separately under the LPPSA rules in force that day.
- Ask a lawyer whether section 8A applies, when the limitation period runs out, and whether to pursue the matter in court or to file a proof of debt with the Department of Insolvency.
- Deal with the official rehabilitation scheme together with the other buyers in the same phase. Make any additional payment only in accordance with the written official scheme.
You can close it this way: Once you have already bought and then face an abandoned project, first confirm the official status, then deal with the loan, the complaint and the rehabilitation. Do not stop the payments first, and do not rest your hopes only on the sentence “the government will take over”.
The above is general information, not legal or financing advice. Whether a project is listed as abandoned, the actions that can be taken, and the loan and rehabilitation arrangements, follow the TEDUH lists on the day, the Ministry’s handling of the case, your contract, and your lending bank’s written reply.
Source
- National Housing Department: definitions of sick developers and abandoned projects (a sick project is progress lagging by more than 30% or an expired contract period; an abandoned project includes no significant works for six continuous months, a winding-up petition, a Receiver and Manager, or a written admission by the developer that it cannot continue, and still requires Minister’s certification; the page writes section 11(1)(c); updated 2023-10-06; checked 2026-11-13)
- National Housing Department: Abandoned Project Rehabilitation Division (definition; Minister’s certification under section 11(1)(ca); confirmation letter; rehabilitation assessment; rescue contractors; support letters for a rehabilitation scheme under section 8; and coordination with banks, the developer, the liquidator and buyers; updated 2023-10-23; checked 2026-11-13)
- National Housing Department: entry point for abandoned-project reports (the page states that the lists are looked up on TEDUH; shows an update on 2026-02-09; checked 2026-11-13)
- TEDUH (entry point for lists of sick and abandoned projects; checked 2026-11-13)
- National Housing Department: FAQ on abandoned housing (limits if the project has not been formally declared; the confirmation letter’s role for bank restructuring, a second EPF withdrawal and LPPSA; how to apply and the documents required; rehabilitation enquiries; advice to claim by registered post or to file a proof of debt with the Department of Insolvency before limitation expires; updated 2023-10-10; checked 2026-11-13)
- National Housing Department enforcement FAQ (item 4: department action when a developer does not continue a project, and the buyer’s ability to go to court under the contract; item 6: Tribunal limit of RM50,000; item 11: rehabilitation progress is queried with the Rehabilitation Division; updated 2023-10-07; checked 2026-11-13)
- TEDUH FAQ (comments, complaints and enquiries to the National Housing Department are directed to SISPAA: https://kpkt.spab.gov.my/; checked 2026-11-13)
- Ministry of Housing and Local Government: Tribunal for Homebuyer Claims FAQ (TTPR does not hear abandoned-project cases; residential, Peninsular Malaysia and Labuan; limit of RM50,000 per claim; a higher amount only with both parties’ written agreement; time limits and filing fees follow the official site on the day; checked 2026-11-13)
- Malaysia Federal Legislation portal: Act 118 (section 11(1)(ca): the Minister may certify that the licensed housing developer has abandoned the housing development; section 11(1)(c) is a separate power to assume control; section 8A: a statutory right to terminate the SPA in the stated conditions, with a refund free of interest within 30 days; section 8A applies only to agreements entered into after the relevant amending Act came into operation; checked 2026-11-13)
- Malaysia Federal Legislation portal: Amendment Act 2012, A1415 (section 8A was introduced by this amendment; for the commencement date, follow the portal text on the day; checked 2026-11-13)
- Ministry of Housing and Local Government: list of related legislation (Act 118 and the 1989 Regulations, including the prescribed SPA formats in Schedule G and Schedule H; checked 2026-11-13)
- Ministry of Finance: Budget 2027 tax measures appendix (Appendix 17: for rehabilitation of abandoned projects confirmed by the Ministry of Housing, a 100% stamp duty exemption is proposed on loan agreements and instruments of transfer completed by the rescue contractor or developer and by the original purchaser from 2027-01-01 to 2030-12-31; the appendix states that, for original purchasers, this includes loan agreements for “additional financing”; a similar exemption previously applied from 2013-01-01 to 2025-12-31; document created 2026-10-26; checked 2026-11-13)
- Ministry of Housing and Local Government: Budget 2027 media statement (full stamp duty exemption on loan agreements and instruments of transfer by original purchasers and by rescue contractors or developers, 2027-01-01 to 2030-12-31; the target is zero abandoned housing projects by 2030; 2026-10-09; checked 2026-11-13)
- Malaysian Department of Insolvency: Proof of Debt form (official entry point for the form used to file a proof of debt when the developer is wound up; checked 2026-11-13)
- National House Buyers Association: About us (HBA describes itself as a voluntary, non-governmental, non-profit, non-political organisation; checked 2026-11-13)
Was this article helpful?